At a glance
Location: Kosova.
Ageing DC plant replaced on a live core site without a single loss of autonomy on the 48 V bus.
Location: Kosova.
Replace end-of-life rectifier shelves and battery strings on a core site carrying live subscriber traffic. No planned outage was available and the DC bus had to stay within its design autonomy throughout.
A staged cutover plan, temporary parallel supply, and phased string replacement so the site never dropped below its minimum reserve.
The site returned to full documented autonomy with a measured baseline for every string, and moved onto a scheduled maintenance contract with annual impedance testing.