At a glance
Location: Kosova and Albania.
Every location had a different unit from a different decade. The cost was not the hardware, it was that nothing could be kept in stock.
A mixed estate of inherited UPS units consolidated onto one platform, one spares pool, one service plan.
Location: Kosova and Albania.
Survey the installed base across locations, agree one standard platform per load band, and put the estate on a single maintenance regime.
A site-by-site survey, a standard specification per load band, and a phased replacement plan aligned to store trading hours.
Faults are now resolved with a stocked regional part instead of a lead-time order, and the maintenance plan is one document rather than dozens.